Scrum Sprint Commitment Rant

Going on a Rant

If there’s one thing that makes me mad whenever I see it is teams abusing the commitment concept in scrum. I’ve been on a rampage against dysfunctional sprint commitments for a while now, but lately my thoughts have crystalized a bit, especially when I had a chance to discuss this with Jim benson, Alan Shalloway, Chris Hefley and Jon Terry last week at Lean Kanban Benelux 2011.

Background

So what is the problem? Well quite often you see scrum teams that finish sprints out of breath, out of quality, out of joy. You also teams that start the sprint full of numbing fear, set a low bar and that low bar becomes a self-fulfilling prophecy. Add to that Product Owners, Scrum Masters and managers all spending precious time worrying about whether we are able to make accurate sprint commitment, instead of working to improve the actual capability of the team.

It’s quite sad actually. Surely that’s not what scrum should look like and indeed other teams have energized focused sprints where they deliver what they can, stretch their abilities just the right amount and finish a sprint with just the right energy and mindset to joyfully go into the next one.

So what’s causing this?

Well, let’s start with the out of breath teams. It typically starts with unrealistic commitments they make in the sprint planning. They make those commitments either because they’re pushed to do it explicitly or implicitly. Yes, scrum says the team should pull according to their capability. But something about the way this all works de-emphasizes actual capability of the team and motivates them to try to take on more than they can handle.
With this in play, they start and since there is a lot in their sprint backlog they have the green light to start many things in parallel. A few days later, in the last mile of the sprint, it’s still many items in progress and it’s either an unsustainable effort to reach the finish line, cutting corners or having a very disappointing sprint result. In our #LKBE11 discussion we referred to those as mini-death-marches…

With teams living in fear it is a different but related story. It starts with the message/spirit conveyed to them by their Product Owner, managers or previous life management culture. When they hear commitment they hear “miss that and you’re in trouble”. And if the ecosystem is such that meeting the sprint commitment is more important than the overarching purpose of the project/release/feature they will be driven to satisfy what they perceive as important – being predictable at the sprint level. So they make a safe commitment. Usually this is achieved by taking safety in the estimates. And so starts a self-fulfilling prophecy, as described by Parkinson’s law and Donald Reinertsen’s principle of the expanding work.

It doesn’t help that the team thinks that if they are able to deliver more, there is no turning back – from that point on they will be asked to deliver more on a consistent basis.

Lets pause here for a second – Isn’t it a reasonable expectation? Shouldn’t the team commit and deliver more in the future if they’re able to? The problem is that even during a short 1-4 weeks sprint, there’s still a lot of unavoidable uncertainty and variability. In exactly what we need to accomplish (requirement space), in how to do it (problem space) and also in how much time will we have for it (capacity). A lot of teams try to eliminate this variability and spend a lot of effort on it. Planning meetings grow longer, people’s capacity is planned at the micro-level…

Many teams will oscillate between over-commitment and under-commitment exactly because of this variability of course. They and their management will be frustrated if they’re measure for effectiveness is meeting the commitment. The only way to consistently meet a commitment is either unsustainable pace, or making a really safe commitment.

Lets eliminate commitment

Well, just as an exercise for now, to see why it’s there in the first place…

Without a sprint commitment, how will the sprint look like? Probably we will see people taking on work from all over the place. They will start at the top priority, but their nature will lead them to start many other backlog items since there is no focusing force urging them to stop starting and start finishing. So we need commitment, or something else, to encourage a team to focus on a few things and finish them first. An alternative to commitment at the stories level is to say we are focusing on a single feature so let’s finish it before moving on to anything else.

Commitment as a Focusing mechanism

Wait – this is the Scrum Sprint Goal – Teams are supposed to agree on a Sprint Goal they will focus on. The detailed story level commitment is an elaboration on that anyhow. If our product backlog is very fragmented and not feature oriented we will have a tough time using an effective sprint goal though. This is something to wonder about in and of itself… but if it’s indeed the business reality that we are doing many small things, we need another focusing guidance. That guidance can be “we think we can finish at least 8 stories, hopefully 4 more, so lets start with 8, get a good feeling we can finish them, and ONLY THEN move on to the 4 others”. Here, the team is still using the sprint commitment, but they’re using it for themselves as a focusing / work in process limiting mechanism.

Containers

Another problem we might have without commitment is that the work will expand uncontrollably. There is no finish line so there is no container. One thing that might help is very energizing purpose of where we need to get at the end of the Feature/Project/Release and why it needs to be at a certain point in time. Seeing our progress towards that goal (or lack of progress…) will help energize our efforts and reduce the expansion of work.

Commit to Capabilities Improvement

Another thing that might help is to start looking at our capability as a team and make a commitment not to exactly what we deliver but in general to improve our capabilities. The capability we care about is velocity as well as ability to turn out the top priority items in the backlog as soon as possible since they are the highest priority. So let’s monitor our capabilities over time and try to make them more predictable first and improve them as a next step. Specifically, measuring Velocity can be done without making any sprint commitment. Just track the velocity for each sprint, preferably on a control chart so you can start to understand the variability in your capabilities.

How can we make promises without commitment?

This is a point I love. On one hand Agile diehards say there is no commitment in agile – “we will just work sprint to sprint and avoid any clear external commitment the business can count on”. On the other hand if you start a discussion about losing the sprint commitment they and others start talking about “how can it even work without the team making a clear commitment and sticking to it?”. Bottom line, the sprint commitment doesn’t help you one bit in making external commitments and meeting them. It’s simply orthogonal to it. You make external commitments based on size estimations and historical/estimated capabilities. You meet external commitments by monitoring where you are towards them and adjusting scope, resources, pace sprint by sprint. If you use the sprint commitment as you should, it gives you nothing towards that goal. Accuracy in sprint commitments is micro-predictability. The business cares about mezzo/macro predictability. Same like a long-term stock investor doesn’t care about the fluctuations within a day or a week, they care about the stock performance over a quarter or a year. The team should care about reducing variability in its capabilities eg. have a lower variability in Velocity, so more aggressive mezzo/macro commitments can be taken on while still allowing safe and sustainable delivery.

How can other teams count on us if we don’t have a clear commitment for the sprint content?

What if we are in an environment where other teams in the group/portfolio count on deliveries from us on a sprint by sprint basis? If we don’t have any commitment how will they know when to expect the delivery from us? If they intend to work in parallel to us, how will they know whether to plan for this or not?

There are a couple of ways to look at this. If 80% of the work is consumed by other teams then we should probably consider the organizational design. Maybe it would be better to work as a single team. Maybe it is a case of us providing a service that is consumed by many other teams, and then it might be better to move towards a pull system – where there is less reliance on dates and rather an agreement on priority, an understanding of the capability in the form of typical lead time from requesting a service from us to the time we deliver it, and then the consumers using that service whenever it is ready, either at their next sprint, or even better as soon as its ready. If you’re thinking this will make planning sprints more complicated and prone to changes you are right. The solution can be to move to full pull mode at the team level, or reduce the batch size you plan for, meaning shorten the sprint length.

If it’s just sporadic work that others depend on, make sure that is what you start with and make a commitment to deliver it. I wouldn’t be surprised if the term Class of Service comes to mind at this point…

What will be the engine of continuous improvement if we don’t have a target commitment to strive for?

Scrum is about Continuous Improvement, right? What drives this? Isn’t it the need to meet commitments? to be better about commitments?

Well, not exactly. The thing that is driving Continuous Improvement is the fact that there is a container, composed of a certain scope to focus on, a certain time to do it in, and the people/capacity to do it with. Think of circling the team with a rope telling them now move together towards the target. This will cause a lot of pain. Some people are faster, others are slowing the team down. Some impediments come up and cause problems. But the rope keeping the team together is forcing them to deal with the problems rather than defer them by making progress on things outside the container just to maintain the comfortable feeling of progress.

So in order to maintain this improvement-inducing container we need the time, the team, and a certain scope to focus on. We can do that with the Sprint Forecast mentioned before.

One important concept in Continuous Improvement is to have a vision / target condition to strive for. What is that target condition in a Scrum environment? As mentioned above, this typically is to improve capabilities.

Improving throughput/velocity requires more scope in each container.

How do we translate improving business agility to the container? The ability to define a shorter time frame that the team can still deliver in. The shorter the time frame the more opportunities to change direction without causing waste. Problem is that there is a limit to this. Work takes time, and there’s a limit to how small we can slice it to still be able to use a container of this structure. That is why, at some level, in order to improve business agility even further, we need to move to another form of container, one which limits the amount of things we are working on as a team at each point in time.

(Clarifying note – If you’re reading this to mean get to a certain level with Scrum then move to Kanban, that’s not what I mean. You indeed will benefit from Kanban at this level, but you can start your journey with Kanban in the first place, or move to it regardless of where you are on the way)

So can we get rid of the Sprint Commitment or not?

Well, my personal opinion is that we can live without a Sprint Commitment as currently practiced by the majority of Scrum Teams out there. It seems the creators of Scrum think along similar lines, as they replaced Sprint Commitment with Sprint Forecast in the latest Scrum Guide

I personally think commitment is important, it’s only a question what you commit to. I prefer to focus on the following types of commitments:

  • Commit to learn about your capabilities, care about them and continuously improve them, by using a focusing mechanism challenging the team as a whole.
  • Commit to deliver the class of service that the business and other teams expect, which means delivering on time when it matters, delivering the most throughput when it matters more, etc.

 

Some more ideas to try at home…

Before we conclude this long post – Some related experiments you might want to try at home…

  • If you feel you are over stretching, For a few sprints try setting a very low forecast and meeting it and see how it looks like. Talk about it. Learn from it.
  • Try limiting the amount of Features/Goals in one sprint. Talk about what it changes in the energies and focus of the team. If you cannot set a limit, that’s an interesting discussion in and of its own, that you should have.
  • Use the Sprint Goal and Sprint Stretch more aggressively. Set a lower goal, and commit to deliver the goal first, and as much of the stretch as possible. Goal should be something you can consistently deliver 95% of the time. (Mike Cohn recommends basing that goal on the mean of the 3 worst sprints out of last 8, another way is to use 2 standard deviations below the mean if you want to take a more statistics oriented approach). whether 95%, 85% or lower is your call. But the expectation should be that if there is a difficulty meeting even this commitment, it’s not forbidden to pick up the pace a bit in order to meet a commitment. Learn from it at the end of the sprint and plan more effectively next time.
  • Read about the XP Planning Game and try it… Seems the idea that iterations can be effective without a commitment is not a new one :-)

Extra Reading

Conclusion

Scrum has some good things going for it. The Scrum-style Planning Game and Sprint Commitment as currently understood and practiced by most teams and organizations is not one of them. I hope this post will help at least some of those improve their results as well as their happiness.

🔔 Before You Go, Subscribe To Blog Updates

Did you like this article? Subscribe now to get notified when new articles, resources, and events are published.

We don’t spam!

19 thoughts on “Scrum Sprint Commitment Rant”

  1. Predicting the unknowable is a risky business. The only valid method of prediction is to use historical information in the form of data, performing statistical analysis on this data to determine the upper and lower control bands. When a system has a control model that is stable (define stability in terms of sigma), one can then determine if it is trending out of control. There will, even in a stable system, be outlyers that are the result of special causes and are NOT indicators that the system is out of control.

    If one is having trouble envisioning the futility of taking discrete measurements in a system and determining success or failure based upon those measurements without first understanding the control band I recommend reviewing E.W. Deming’s Red Bead Experiment. Sometimes the players “get it right” sometimes they don’t, but it is all simply statistical uncertainty.

    The key success mechanism in agile are PULL get the signal when the next thing is needed) and ITERATIONS (learn where assumptions were wrong sooner rather than later). These are the only means of reacting appropriately to the variability in the system. Note that they CANNOT remove the variability, but they can allow the best reaction to the variability and uncertainty.

    Techniques beyond these are not wrong headed but they tend to rely on the exact things we have that traditional project management does; predicting those things that are not well predictable and ascribing certainty to the things that are not certain.

    • Thanks for your comment Jim!
      Note I mentioned the change in scrum guidance inside the post, and am really glad this clarification is now formal and out there.

      I hope the within months/years this post will be obsolete.
      Right now, I think it will take a lot of energy and focus from all of us to change the way organizations and the scrum world think about this.

      Let’s survey CSMs what they think commitment is about, and monitor the change over time :-)

  2. Just the post I was about to write – and I find you’ve read my mind written it for me. My thanks :)

    Some observations:

    1) “The only way to consistently meet a commitment is either unsustainable pace, or making a really safe commitment.” – unsustainable pace is, by definition, unsustainable and therefore not open for *consistently* meeting commitments. That only leaves us with the latter: setting the bar low and making safe (under) commitments. Put another way, then, demanding that teams consistently meet their commitments will inevitably drive them to playing safe and under-committing.

    2) “I personally think commitment is important, it’s only a question what you commit to.” Agreed. And I would add one more bullet to your list:
    o Personal commitment – each team member commits (to themselves and to each other) to do their very best to deliver on (the essence) of the Sprint Goal, whilst understanding that natural variation might well mean that certain of the planned deliverables don’t actual get fully completed in any given sprint, and that’s OK.

    I’m off now to write a post about how time-boxing and commitment best play well together – unless you’ve already written that too? :)

    Cheers
    – Bob @FlowchainSensei

  3. ” And if the ecosystem is such that meeting the sprint commitment is more important than the overarching purpose of the project/release/feature they will be driven to satisfy what they perceive as important – being predictable at the sprint level.”

    Amen to that. The commitment essentially becomes an arbitrary target and hitting the target becomes the point of coming into work in the morning rather than working towards the real purpose of the company/project/team.

    Invariably such targets take no account for the variation inherent in the nature of software development. It is what Reinertsen calls ‘One Time Work’ – i.e. You never do the same thing in the same way twice.

    Thank you for this rant. It chimes with a lot of my current Systems Thinking led thinking on this subject.

  4. You could eliminate commitment, but I think this mini-death march is trying to tell you something: you have to change something about your work system to eliminate the death march. I think eliminating commitment is a mistake, because it underestimates the importance of the relationship to the customer.

    Of course, in some organisations, there is no real customer — there might be an internal person whom someone tapped on the shoulder one day and said, “You! Be the product owner!” I find a strong correlation between the problem you describe and the presence of one of these customer stand-ins. I’m sure there’s a clue there.

    It’s hard to give advice in such a general situation, but I think throwing away commitment perpetuates the notion that this way of working constitutes a mere programmer revolution, and doesn’t actually improve the product nor the work system. The team might need a 3-month breather while it gets some parts of its house in order, establishes a better delivery pipeline, writes more tests, whatever… but giving up on the commitment indefinitely — that sounds awfully risky.

  5. Very nice article. I am a new Project Manager . Your article gave me a
    good idea of where we need to start improving/changing things.I appreciate the
    writings.i got my trainnings on scrum.

Comments are closed.